Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Blacksnake Creek StormWater Separation Project
 

Project Information

Blacksnake Creek StormWater Separation Project
513-010

Project Manager: David Frazier

Assistant Project Manager: Lee Sommers

Current Project Status: Construction

Project Scope:
    The Blacksnake Combined Sewer Rehabilitation Crack Repair package generally consists of repair of concrete and brick cracks in the Blacksnake Combined Sewer pipeline, removal of encrustation and deposits at select lateral connection locations, surface repair of plugged lateral connections and repair of existing missing brick locations. The Blacksnake Creek Stormwater Separation Project Tunnel Package generally consists of the construction of 90-inch diameter concrete precast segment lined 6,648-foot long tunnel, 37-foot diameter baffle drop shaft, 48 feet of near surface reinforced concrete box culvert, 2-foot diameter vent shaft, l8l feet of 90-inch diameter open cut steel pipe installation, l25 feet of 90-inch jacked steel pipe, an energy dissipation structure and site restoration. The Blacksnake Creek Stormwater Separation Improvement Conveyance Package generally consists of the construction of a 7-feet by 6-feet below-grade precast box culvert 5,729 feet in length with four junction structures and an inlet structure, construction of an inlet structure to the existing Blacksnake Combined Sewer System, rehabilitation of a screening structure and slide gate within the existing Blacksnake Combined Sewer System, improvements to approximately 900 linear feet of the existing Roy’s Branch channel near the Missouri River and site restoration.  

Project Funding:
   2015 A IDA Bonds
   2016 SRF Funding
   2017 SRF Funding
   Over-payment from Property Closings
   Recovery Reimbursement
   SEWER FUND BAL

Project Funding Amount: $87,000,000.00

Update:
   Blacksnake Combined Sewer Rehabilitation Crack Repair: Projected closed out. Blacksnake Creek Stormwater Separation Improvement Project Tunnel Package: Super Excavators has entered the tunnel 760-ft-ft and has installed 190 ring segments of the tunnel. There are some mechanical issues that have stopped progress now. Super Excavator’s will be leaving Friday the 20th and return after the first of the Year. The first of February their subcontractor Foley will be installing the floor of the drop shaft. Blacksnake Creek Stormwater Separation Improvement Project Conveyance Package: Mega’s Subcontractor WIC has completed the apron in front of the inlet structure. January 4th Decker will be back on site near the Nature Center to work on the cut off wall on the Roy’s Branch Creek near the outfall structure. CSO Sluice Gate Repairs Kissick Construction mobilized on site December 9th and are setting up the site for the mobilization of the dewatering and the shoring subcontractors.  

Last Update: Friday December 21, 2018