Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Hyde Park Ball Fields & Splash Pad
 

Project Information

Hyde Park Ball Fields & Splash Pad
313-300

Project Manager: Jeff Atkins

Assistant Project Manager: Chuck Kempf

Current Project Status: Design

Project Scope:
   This section of Hyde Park, is in the design phase, to see the cost of turning the Hyde Pool into a Splash Pad, and to demo the current pool. Complete Renovation of all fields and structures, new lights on 3 fields, replace and add bleachers, parking lot overlay. 

Project Funding:
   BODE TRUST
   Cell Phone
   CIP Sales Tax
   DONATION
   MDNR GRANT

Project Funding Amount: $1,954,464.00

Update:
   The Hyde Park Ballfield Bleacher Covers have been completed. Final paperwork and payment is in process. 

Last Update: Tuesday July 31, 2018