Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Hyde Park Ball Fields
 

Project Information

Hyde Park Ball Fields
313-300

Project Manager: Jeff Atkins

Assistant Project Manager: Chuck Kempf

Current Project Status: Complete

Project Scope:
   This section of Hyde Park, is in the design phase, to see the cost of turning the Hyde Pool into a Splash Pad, and to demo the current pool. Complete Renovation of all fields and structures, new lights on 3 fields, replace and add bleachers, parking lot overlay. 

Project Funding:
   BODE TRUST
   Cell Phone
   CIP Sales Tax
   DONATION
   MDNR GRANT

Project Funding Amount: $1,829,274.00

Update:
   Project design of the splash pad is scheduled for FY-20. Construction in FY-21 

Last Update: Wednesday April 3, 2019