Civic Center Park Balustrade & Stonework Repair
313-405

Project Manager: Bob Todd

Current Project Status: Bidding and Award

Project Scope:
   The work consists of repairs to the stonework of the City Hall balustrades, including adjacent stone to ground level. Repairs to Civic Center Park missing balustrade. 

Project Funding:
   CIP Sales Tax
   Recovery Reimbursement

Project Funding Amount: $357,972.00

Update:
   This project consists of the repair and/or replacement of stone balustrade sections, top rails and various stonework repairs at Civic Center Park. Work is expected to begin in April 2018. 

Last Update: Thursday March 29, 2018