New Fire Station (Station 9)
 

Project Information

New Fire Station (Station 9)
313-200

Project Manager: David Simpson

Assistant Project Manager: Mike  Dalsing

Current Project Status: Construction

Project Scope:
   To Build 2 New Fire Stations: Use Station 12 savings and Geiger Mansion proceeds to acquire land for three stations. This station will be called #9 The address of this station will be 3202 Faraon Street. 

Project Funding:
   CIP Sales Tax

Project Funding Amount: $3,410,621.61

Update:
   The contract for construction was awarded to E.L. Crawford Construction Company, and work is underway at the site. All the roof trusses are set with most of the roof decking installed and waterproofing membrane installed. Work has started on the metal roof. The concrete parking lot and curbs are complete. Most of the exterior wall brick masonry is complete. Interior framing and drywall work is ongoing. Fire Station 9 is ~60% complete with final completion set for July 14, 2018.  

Last Update: Wednesday January 31, 2018