New Fire Station (Station 9)
 

Project Information

New Fire Station (Station 9)
313-200

Project Manager: David Frazier

Assistant Project Manager: Mike  Dalsing

Current Project Status: Construction

Project Scope:
   To Build 2 New Fire Stations: Use Station 12 savings and Geiger Mansion proceeds to acquire land for three stations. This station will be called #9 The address of this station will be 3202 Faraon Street. 

Project Funding:
   CIP Sales Tax

Project Funding Amount: $3,410,857.78

Update:
   station is completed and open. three days of open house were well attended. Staff is finishing up with final furniture and equipment purchases  

Last Update: Wednesday August 29, 2018