Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Karnes Road/Parkway Realignment
 

Project Information

Karnes Road/Parkway Realignment
313-015

Project Manager: Lee Sommers

Assistant Project Manager: Andy Clements

Current Project Status: Construction

Project Scope:
   Realign Karnes through North West Parkway to eliminate intersecting at St. Joseph Avenue and Extending Cook Road from St. Joseph Aveenue to Savannah Road. This also uses 2008 CIP 2.4 million  

Project Funding:
   CIP Sales Tax
   SRF FUNDING

Project Funding Amount: $3,086,445.86

Update:
   Herzog has completed the base layers and toping layers of the asphalt on NW Parkway and Karnes. The rock lining the drainage ditches has been completed. Sidewalks and trail sections in the area have been completed. Street Lighting has been completed. Signage and striping is in progress. 

Last Update: Monday July 16, 2018