Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Cook Road Extension
 

Project Information

Cook Road Extension
313-020

Project Manager: Brady McKinley

Assistant Project Manager: Roger Sparks

Current Project Status: Construction

Project Scope:
   Extending Cook Road from St. Joseph Aveenue to Savannah Road. This uses 2008 CIP 2.4 million  

Project Funding:
   CIP Sales Tax

Project Funding Amount: $2,861,114.29

Update:
   Box culvert construction is underway with other storm water improvements and earthwork happening concurrently. This project was originally scheduled to be complete by September 1, 2017 and due to unforeseeable delays caused by high water tables the final completion date has been moved to November 15, 2017.  

Last Update: Wednesday August 30, 2017