Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Cook Road Extension
 

Project Information

Cook Road Extension
313-020

Project Manager: Brady McKinley

Assistant Project Manager: Brady McKinley

Current Project Status: Construction

Project Scope:
   Extending Cook Road from St. Joseph Avenue to Savannah Road. This uses 2008 CIP 2.4 million. This project will have sidewalks added on the West side of Cook Road. 

Project Funding:
   CIP Sales Tax

Project Funding Amount: $2,930,016.95

Update:
   Substantial completion was achieved on November 28, 2017 and the roadway was opened to traffic. The contractor continues clean-up of the site and sidewalk construction. KCPL will be completing the installation of the street lighting the first week of December. Final completion of the project is expected in mid-December 2017.  

Last Update: Wednesday December 19, 2018