Mansfield Road
 

Project Information

Mansfield Road
313-035

Project Manager: Brady McKinley

Assistant Project Manager: Roger Sparks

Current Project Status: Construction

Project Scope:
   Mansfield Road from 9th to 22nd. Street Flatten, Widen to 12 ft lanes, improve drainage and add sidewalks. 

Project Funding:
   CIP Sales Tax

Project Funding Amount: $2,000,000.00

Update:
   Contractor is completing handrail along sidewalk as weather permits. All other project items are complete and the roadway has been open to traffic since September. Beginning right of way acquisition for Phase 2 of the Mansfield Road Reconstruction project. Offers have been made on eighteen properties for temporary easements and right of way. Right of way clearance is expected to be complete by late January with an advertisement and bid opening in February 2018. Phase 2 limits of construction will be between South 14th Street and Southwest Parkway. Construction will be expected to begin in Late April 2018 and be completed in early August 2018. 

Last Update: Wednesday November 29, 2017