Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Mansfield Road Phase 2
 

Project Information

Mansfield Road Phase 2
313-035

Project Manager: Rick Spriggs

Assistant Project Manager: Brady McKinley

Current Project Status: Construction

Project Scope:
   Mansfield Road from Southwest Parkway west to 14th Street. Widen to 12 ft lanes, improve drainage and add sidewalks on south side. 

Project Funding:
   CIP Sales Tax

Project Funding Amount: $2,613,080.00

Update:
   All work is done except for the street lights and they are in the process of getting them finished up and working. The road is now back opened. 

Last Update: Thursday September 27, 2018