Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
FY15 City Residential/Commercial Shared-Cost Sidewalk Replacement Program
 

Project Information

FY15 City Residential/Commercial Shared-Cost Sidewalk Replacement Program
313-050

Project Manager: Judy Hovey

Current Project Status: Construction

Project Scope:
   FY15 City Residential/Commercial Shared-Cost Sidewalk Replacement Program. This program shares the cost of sidewalk replacements for residental and commercial business. 

Project Funding:
   CIP Sales Tax

Project Funding Amount: $150,000.00

Update:
   As of February 28, 2017 all of the funds for the FY 15 funds has been appropriated for projects. The only money left to pay out is the project at City Hall. This is still the status. 

Last Update: Wednesday April 26, 2017