Urban Trail Phase 20, Riverside Extension Part 2
 

Project Information

Urban Trail Phase 20, Riverside Extension Part 2
313-120

Project Manager: Rick Spriggs

Assistant Project Manager: Roger Sparks

Current Project Status: Design

Project Scope:
   To construct an Urban Trail extension on Riverside Road from Faraon Street to Messanie Street. Calling this Riverside Phase 2 

Project Funding:
   CIP Sales Tax
   MPO/STP-Funds
   Transportation Alternative Program (TAP)

Project Funding Amount: $350,081.08

Update:
   TNR Construction was given the Notice to Proceed on September 5, 2017. The project has been staked and the contractor has been moving dirt from the south end of the project. Culvert pipe has been delivered to the project and the contractor has been installing them. 

Last Update: Tuesday September 26, 2017