Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
2015 Urban Trail phase 21, Patee Branch, phase 1
 

Project Information

2015 Urban Trail phase 21, Patee Branch, phase 1
313-130

Project Manager: Rick Spriggs

Assistant Project Manager: Roger Sparks

Current Project Status: Construction

Project Scope:
   Construction of the Urban Trail extension from 36th Street to 31st street. 

Project Funding:
   CIP Sales Tax
   MPO/STP-Funds
   Transportation Alternative Program (TAP)

Project Funding Amount: $427,922.00

Update:
   The contractor all the drainage structures in place and continues moving dirt from the west end of the project to the east end to get the project to grade. Overall the project is about 25% complete. 

Last Update: Friday November 30, 2018