Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
2015 Urban Trail phase 21, Patee Branch, phase 1
 

Project Information

2015 Urban Trail phase 21, Patee Branch, phase 1
313-130

Project Manager: Rick Spriggs

Assistant Project Manager: Roger Sparks

Current Project Status: Land Acquisition

Project Scope:
   Construction of the Urban Trail extension from 36th Street to 31st street. 

Project Funding:
   CIP Sales Tax

Project Funding Amount: $855.00

Update:
   The School property and the railroad property are on its way to council for approval. We have also received word from the other two property owners and are in the process of working with them on acquiring their property. 

Last Update: Tuesday September 26, 2017