Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
2018 Urban Trail Phase 24 from 13th Street to 20th Street
 

Project Information

2018 Urban Trail Phase 24 from 13th Street to 20th Street
313-145

Project Manager: Rick Spriggs

Current Project Status: Land Acquisition

Project Scope:
   To build a trail from 20th Street to 28th Street 

Project Funding:
   CIP Sales Tax

Project Funding Amount: $4,625.00

Update:
   A meeting with the title company that gives us the O & E's for each of the properties needed for the project and go over what kind of information we need for these properties. 

Last Update: Friday January 26, 2018