Airport Wildlife Fence
413-040

Project Manager: Abe Forney

Assistant Project Manager: Roxanne Patton

Current Project Status: Construction

Project Scope:
   Installation of an 8 foot chain link fence around the Rosecrans Memorial Airport property.  

Project Funding:
   Airport CIP
   Airport's 2017 Discretionary Funds
   FAA GRANT
   MO ANG GRANT
   MODOT BLOCK GRANT

Project Funding Amount: $3,146,013.50

Update:
   Consultant (Jviation) continues submittal review for AmeriFence materials. Jviation sent the Construction Observation Program (COP) to MoDOT on November 20, 2017. Construction anticipated to start January 8, 2018. A Notice to Proceed (NTP) will be issued upon more discussions with AmeriFence. 

Last Update: Tuesday December 12, 2017