Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Airport Wildlife Fence
 

Project Information

Airport Wildlife Fence
413-040

Project Manager: Abe Forney

Assistant Project Manager: Roxanne Patton

Current Project Status: Construction

Project Scope:
   Installation of an 8 foot chain link fence around the Rosecrans Memorial Airport property.  

Project Funding:
   Airport CIP
   Airport's 2017 Discretionary Funds
   FAA GRANT
   MO ANG GRANT
   MODOT BLOCK GRANT

Project Funding Amount: $3,146,013.50

Update:
   Contractor continuing work on all facets of the fence at once. -95% of the fence posts are installed. -75% of the chain link is installed. -60% of the wildlife fence is installed. -70% of the barb wire is installed. -The north road will be relocated and moved to the north beginning June 11  