Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Brown's Branch Pump Station
 

Project Information

Brown's Branch Pump Station
513-180

Project Manager: Jake Fisher

Assistant Project Manager: Lee Sommers

Current Project Status: Construction

Project Scope:
   to provide design services for the installation of one mechanical bar screen to replace one of the existing bar screens, A conveyor and washer/compactor to transport material from the screen room to the dumpster located outside the existing building.  

Project Funding:
   SEWER FUND BAL
   Water Protection Operating Fund

Project Funding Amount: $1,286,650.00

Update:
   Construction continues on the Plant pump station and Brown's Branch. Browns Branch - Screen #1 has been installed along with compactor, the removals in the north wall of the facility how been infilled with CMU. Electrical work has begun on the facility in order to get the new screen in operation. Upon startup of the newly installed screen, the second screen will be removed and replaced. Plant Pump Station - Screen and compactor have been installed; installation of control panel and wire equipment to be completed the week of the 23rd. start up of new bar screen to begin the week of 7-31 

Last Update: Monday July 23, 2018