Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Brown's Branch Pump Station
 

Project Information

Brown's Branch Pump Station
513-180

Project Manager: Jake Fisher

Assistant Project Manager: Lee Sommers

Current Project Status: Construction

Project Scope:
   to provide design services for the installation of one mechanical bar screen to replace one of the existing bar screens, A conveyor and washer/compactor to transport material from the screen room to the dumpster located outside the existing building.  

Project Funding:
   SEWER FUND BAL
   Transfer from Water Protection Fund
   Water Protection Operating Fund

Project Funding Amount: $1,324,428.00

Update:
   Delivery of the SSTL slide gates is scheduled for the first week in December, the crews are planning to be on site the following week to begin the replacement. This will complete the project.  

Last Update: Tuesday November 27, 2018