Capital Project Tracking and Reporting SystemCity of St. Joseph, Missouri
Brown's Branch Pump Station
 

Project Information

Brown's Branch Pump Station
513-180

Project Manager: Lee Sommers

Current Project Status: Construction

Project Scope:
   to provide design services for the installation of one mechanical bar screen to replace one of the existing bar screens, A conveyor and washer/compactor to transport material from the screen room to the dumpster located outside the existing building.  

Project Funding:
   SEWER FUND BAL
   Water Protection Operating Fund

Project Funding Amount: $1,286,650.00

Update:
   Garney is in the submittal process and is expected to start construction May 8th in conjunction with the first progress meeting. 

Last Update: Friday April 27, 2018