WPF Levee Stormwater Pump Station
 

Project Information

WPF Levee Stormwater Pump Station
513-195

Project Manager: Lee Sommers

Current Project Status: Design

Project Scope:
   Interior Drainage Stormwater Pump Station. The scope of work services to be rendered by the Engineer under the Pre-Design, site analysis and schematic design for the stormwater pump station improvements project located south of the City of St, Joseph Water Protection Facility, new the Missouri Avenue Outfall.  

Project Funding:
   2018 Conventional Bonds

Project Funding Amount: $5,000,000.00

Update:
   Station HDR the City’s Engineering Consultant and City Staff reviewed the technical requirements along with Request for Qualifications for the Fixed Price Design-Build (RFQFPDB) portion of the project. Tentative date for the Issuance for the RFQFPDB is December 17. 

Last Update: Wednesday November 28, 2018