2017 Urban Trail system Maintenance
313-150

Project Manager: Rick Spriggs

Current Project Status: Project Initiation

Project Scope:
   to repair all the concrete cracks on the older Trails throughout the city. 

Project Funding:
   CIP Sales Tax
   MPO/STP-Funds

Project Funding Amount: $342,393.63

Update:
   No new progress has been made on the project due to a wet late winter and early spring. The subgrade has not drying out enough to do any earthwork on the project. 